1992 Project Evaluation Results
Prepared by the Policy, Planning and Evaluation Unit (PPEU)
Tables
Table No. 1 - Project Strengths
| STRENGTHS/ ACHIEVEMENTS | GAM/86/C02 | UGA/85/C03-4 | NIC/80/CO3 | NIC/84/C01 | STP/87/C02 | BOT/87/C02 |
| Sound Project Concept | X | X | X | P | X | X |
| Beneficiaries Well Identified | X | X | X | X | X | X |
| Proper Identification of Needs | X | X | * | * | P | X |
| Full Attainment of Objectives | P | * | P | * | P | X |
| Effective TA | * | * | * | * | P | P |
| Good Technical Design | X | * | X | * | P | P |
| Effective Community Participation | P | * | * | * | * | N/A |
| Sufficient Participation by Women | * | * | * | P | * | N/A |
| Effective Utilization of Outputs | X | X | X | * | X | X |
| Effective Maintenance | X | X | X | * | P | X |
X: Yes *: No
P: Partial N/A:
Not applicable
Table No. 2 - Project Weaknesses
WEAKNESSES/ PROBLEMS
GAM/86/C02
UGA/85/C03-4
NIC/80/CO3
NIC/84/C01
STP/87/C02
BOT/87/C02
Poor Project Formulation/Design
P
P
P
X
P
*
Project Assumptions Not Verified
X
X
X
X
X
*
Poor Technical/ Equipment Specifications
X
X
*
X
P
*
Insufficient Community Sensitisation
*
*
*
X
P
*
High Staff Turnover/Staff Shortage
*
X
*
*
*
*
Lack of Monitoring/Supervision
P
X
P
X
X
*
Insufficient Training
X
X
*
X
X
*
Weak Institutional Capacity
*
P
*
X
*
*
Lack of Project Coordination
X
*
P
X
X
*
Lack of Sectoral Coordination
X
*
X
X
X
*
Under-utilization of Equipment
*
*
*
X
*
*
Procurement/ Recruitment Delays
P
X
X
X
*
X
Time/Cost Over-runs
X
X
X
X
*
X
X: Yes *: No P: Partial N/A: Not applicable