1999 Project Evaluation Results
Prepared by the UNCDF Evaluation Unit
I. Basic Project Data
|
Project Number: |
BGD/77/C35 |
| Type of Evaluation: | Ex-Post |
|
Project Title: |
The Mirpur Resettlement Project |
|
Cooperating Organization: |
Grameen Krishi Foundation (GKF) |
|
Government Executing Agency: |
Housing & Settlements Directorate (HSD) |
|
Sector: |
Human Settlement |
| Date Project Approved: | April 1978 |
| Date Project Began: | October 1986 |
| Date Project Evaluated: | May 1999 |
|
UNCDF Budget: |
US$ 5,197,000 |
|
UNDP Budget: |
387,000 |
|
UNICEF Budget: |
169,000 |
|
Gov't. Budget: |
2,696,000 |
|
Total Budget: |
8,449,000 |
|
UNCDF Expenditures |
5,197,000 |
II. Background
The Mirpur Resettlement Project (BGD/77/C35) originated in the mid-1970s, when the Government of Bangladesh (GoB), through the Housing & Settlements Directorate (HSD), sought to remove some 2,600 households who were squatting on land belonging to the Ministry of Defence in Bashantek. In 1976, the GoB requested UNCDF to assist in the resettlement of these families to an 87-acre site in Mirpur allocated for this purpose. The project was initially approved by UNCDF in 1978. After significant delay caused by a range of extraneous factors, especially the flooding of the site that required earthworks for protection, the project finally started in October 1986 and was completed in December 1992. A grant that eventually totalled $5,197,000 was provided by UNCDF, with additional funding from the GoB ($2,696,000), UNICEF ($169,000) and UNDP ($387,000).
III. The Project
The immediate objectives of the Mirpur project, were three-fold and reflect actions at three distinct levels (project, strategic and policy):
- Project Level:
To resettle 2,600 families in a viable community that provided adequate
services and levels of physical and social security.
- Strategic Level:
To test a Government strategy enabling very low income groups in Dhaka
to have access to land tenure, urban services and housing.
- Policy Level: To strengthen the Governments institutional capacity in the field of social housing.
The project design was for a classic site-and-services scheme, in which the principles of self-help housing were used to provide a basis for the sustainable improvement of peoples housing needs and conditions. International experience with such schemes is mixed, with success usually dependent upon a suitable location, security of tenure, good infrastructure and services and the active compliance of the families being moved.
IV. Findings
The main findings of the evaluation are:
- The self-help
housing model, based around a site-and-services scheme, was successful
in terms of providing a cost-effective means for providing a more
secure and better living environment for the families relocated from
Bashantek.
- The success reflected
the good location, infrastructure provision and security of tenure
that characterised the scheme.
- This process
was based on a good organisational structure that integrated government
agencies, NGOs and the community. This includes confidence that the
initial registration and allocation of plots was fair and transparent.
- It has led to
sustainable livelihood improvements, with both increased incomes and
a major growth in the assets owned by the Baunia residents.
- There is a process
of gentrification taking place, with an active land market developing
and plots being sold to outsiders.
- The main problems
centre on the land registration system. Due to a break-down in the
repayment process within the Government, there were serious concerns
over whether some sections of the population will be allowed to pay
the full dues and therefore receive full title to their plot.
- The project design
was inherently flawed, with an over-concentration on the physical
development of the resettlement estate and no meaningful attempt to
integrate activities that corresponded to project objectives on the
development and institutionalisation of low-income housing policies
and strategies. The component relating to the first objective, the
resettlement of 2,600 households from Bashantek to Mirpur, was very
good, with an approach to resettlement that was appropriate and effective.
The design faults relate to the second two objectives, concerned with
the development and institutionalisation of strategies and policies
for low-income housing. The project contained no meaningful components
to realise these objectives and also failed to include an effective
monitoring and evaluation process that would have addressed these
failings during the projects lifetime.
- The consequence is that the project had no impact on national or Dhaka housing development strategies or policies which currently concentrate on high-rise developments that are not accessible to the poor, and punitive demolition and eviction actions against squatter dwellers. This represents a missed opportunity, for the Mirpur model provides the basis for a sustainable and effective strategy addressing the living environment and livelihood development needs of the urban poor.
V. Results/Impact
The project has resulted in an area that is now a thriving and developing neighbourhood that is characterised by significant improvements to the livelihoods of its residents with expanding infrastructure and housing stock. There are some areas for concern; in particular, the issue of land registration and provision of land titles require closer examination. Despite this, it is clear that the first project objective has unequivocally been met. The evaluation concluded that this was a community that was transforming itself from one of the most underprivileged in the city to one where life was improving and where the future could be viewed with optimism. It is clear that the concept of self-help housing and development that was the rationale behind the project was realised. This experience provides important lessons for improving the position of the poor living in urban slums.
Attainment of the second objective is difficult to assess. At one level it has been met, in that the strategy was tested and proved successful in Baunia. This experience has the potential to serve as a model for wider replication that could form the basis, in part at least, for the resolution of the housing and development problems that the urban poor in Bangladesh face. A matter of serious concern is that there has not existed any form of process whereby these elements of a strategy could be translated into a model that could be applied on a wider basis.
The attainment of the last objective is less ambivalent. No action was taken to strengthen institutional capacities during or after the project. There is no evidence to suggest that the experiences gained during the Mirpur Resettlement Project have in any way informed the policy approach to low-income urban housing. Indeed, all the evidence points the other way, with development approaches concentrating on high-rise housing for the middle classes and a programme of punitive slum demolitions and evictions underway at the time of the evaluation.
VI. Recommendations
Based on these conclusions, the main recommendations of the evaluation team are:
- There is a need
for action to ensure that the final stages of the land registration
and transfer process are successfully completed. The present system
and institutional capacities available are not adequate for this task
and residents are suspicious of the role played by HSD staff. It is
consequently recommended that:
- The rules
concerning instalment payments and final registration are clarified
and widely publicised in the settlement.
- Greater capacity to collect outstanding dues and complete the title transfers is needed. This also needs to be seen to be fair and transparent. It is consequently recommended that an NGO, if possible CONCERN, be contracted to complete this task, and that an external verification of this process takes place.
- The rules
concerning instalment payments and final registration are clarified
and widely publicised in the settlement.
- There is a danger
that the positive experience from Baunia will be lost at a time when
Bangladesh is in a critical need for sustainable solutions to the
low-income housing crisis. The following steps will help to address
this issue:
- The success
of the Mirpur model should be more widely publicised: not just
within the institutions directly involved in its implementation,
but also in the wider public domain so that other institutions
with an interest in this area are made aware of the results.
- The scope for additional support to the sector should be carefully examined, but any such support should be linked to clear conditions and, in particular, should be contingent upon a demonstrated commitment to enhance institutional capacities, initiate policy and legislative reforms and allocate adequate and appropriate lands for such policies.
- The success
of the Mirpur model should be more widely publicised: not just
within the institutions directly involved in its implementation,
but also in the wider public domain so that other institutions
with an interest in this area are made aware of the results.
- The process of
project design, implementation and evaluation needs to be carefully
examined, to ensure that:
- There is
an appropriate relationship between goals, objectives, activities
and outputs.
- The structure
and duration of the project reflects the full development process
with which it is concerned (and not just the period of donor funding).
- There is
a clear and appropriate designation of institutional responsibilities
for all aspects of the project.
- Adequate internal and external monitoring and evaluation processes are integral to the project.
- There is
an appropriate relationship between goals, objectives, activities
and outputs.
VII. Lessons Learned
The key lessons to be learned from the Mirpur Resettlement Project are:
- Good project
design is fundamental to the success of any such process. This design
should ensure that the project -
- Is conceptually
sound, with all aspects of the development process integrated
into the basic model.
- Has an appropriate
range of activities for all objectives, including those that relate
to the process through which positive experiences can be institutionalised.
- Contains
an effective monitoring and evaluation process as integral to
the project.
- Is or a duration
that covers the full process, not just the component where donor
funds are disbursed.
- Is conceptually
sound, with all aspects of the development process integrated
into the basic model.
- The institutional
modalities of such projects are of critical importance, with much
of the success in Baunia reflecting good initial arrangements and
current concerns over land registration and transfers reflecting problems
at this level.
- Participatory
self-help works: the urban poor are willing and able to rapidly improve
both their living environment and their livelihood prospects when
given minimal levels of security and reasonable access to opportunities
and factors of productions such as credit and markets.
- The concentration
on immediate implementation tasks such as land preparation without
considering the wider development context of the project is self-defeating.
In this case, this relates in particular to the creation of a process
that would allow the institutionalization of the Mirpur model once
it proved successful.
- The process of project evaluation is important in creating the conditions where these lessons could be identified. The insights presented in this report would not have been possible without the sort of in-depth field research and analysis that has characterised this evaluation, as initial impressions were extremely different to the final conclusions. Effective external evaluation is an essential complement to a good internal monitoring and evaluation system and needs to be integrated at the design stage.
VIII. Evaluation Team
The evaluation was carried out by:
- John Soussan
(Team Leader)
- Anjan Datta
- Alexandra Clemett





