The LDP has the expressed support of Government of Ethiopia (GoE)/ANRS as it is closely aligned to the governments own strategy and systems. This creates better institutional capacities at all levels. This project is likely to have significant impact on systems building at local level. At woreda level they accept the PRA as a very improtant tool for planning, and at community level. The main achievements of the programme have been:
Alleviating programme-relevant dimensions of poverty
- 4000-5000 people will have easier access to water;
- Irrigation schemes reportedly increase income of farmers. (1000 Birr a season);
- They have also formed 1 cooperative (25 members).
Improving access to infrastructure and services
- 46 schemes (school classroom buildings, health posts, access road project and veterinary health post and especially water boreholes) have the potential to improved services and infrastructure facilities in all three woredas.
Achieving more equitable participation and distribution of benefits across gender, ethnic and socio-economic groups
- LDP has focused on training woreda staff and communities on issues such as: environmental protection, HIV/AIDS, gender mainstreaming, almost 30% of trained artisans are women. Most of the interventions (water, health post) are women's priority;
- Women are part of the woreda PSC but are not yet seen in leadership positions at kebele levels.
Improving management of natural resources
- LDP has facilitated woreda experts to train kabele administrations and community representatives in environmental protection issues;
- However, the intended output of developing natural resource management guidelines has not taken place.
Influencing policy reforms and implementation that support effective decentralisation
- LDP certainly supports effective decentralisation. LDP has tried to influence policy reforms at ANRS level by organising regional workshop and presenting UNCDF approach, systems, planning and budgeting guidelines for local infrastructure investment.
Replication and up scaling of the approach by Government and/or other donors
- Indication that GoE/ANRS are positive towards LDP but still no decision on replication/up scaling. Other donors (bilateral) express interest but have own approach. WB has shown interest.
|